All principal construction work on the gas interconnector between Bulgaria and Greece via Komotini has been completed. Since mid-June the pipeline equipment has been filled and tested successfully with compressed natural gas. The gas pipeline, the seven valve stations, the two gas metering stations and the dispatch centre are technically viable, construction supervision has ascertained.
The Bulgarian-Greek company ICGB, which is the investor and future operator of the interconnector issued a statement denying allegations that the pipeline is unfinished. ICGB has submitted, to the Ministry of Regional Development and Public Works, a two-stage plan for the completion of the accompanying works.
The interconnector can be made operational in test mode at the end of August, ICGB says.
The Ministry of Innovation and Growth has presented the country’s first interactive investment map . The platform aims to provide Bulgarian and foreign investors with useful and up-to-date information in one place, making it easier for them to make..
The Bulgarian state-owed natural gas supplier Bulgargaz has proposed that the price of natural gas for November increases by around 8% to nearly 66 BGN per megawatt-hour, excluding fees and taxes, reported BNR's journalist Yuliana Kornazheva. The..
The growth of the national economy in the second quarter of 2025 accelerated by 3.5% on an annual basis. According to an analysis by the Bulgarian National Bank - BNB, the main factors for the acceleration are the decrease in imports..
KBC Group expects the Bulgarian economy to grow slightly more next year in comparison to its previous forecasts, according to the..
+359 2 9336 661