After 6 months of analyzes and inspections, the Ministry of Environment allowed the completion of the "Struma" highway along the route through the Kresna Gorge. Earlier, the courts also rejected requests of green organisations for a new environmental assessment of the project.
The ministry's decision ends a more than 20-year-long approval process that had delayed the completion of the last 14 km of the highway. The highway leads to Thessaloniki and is part of the route of Pan-European Corridor IV, connecting Central Europe with Greece and the Mediterranean ports. The lack of highway near Kresna creates long traffic jams and leads to frequent road accidents. If construction starts in 2025, completion is expected in 2028.
We agree, Prime Minister, and look forward to continuing our successful cooperation in multiple fields, advancing our shared strength, security, and prosperity , the US embassy in Bulgaria wrote, in connection with yesterday’s brief meeting between..
Vazrazhdane party declared they were opposed to the sale of two Russian reactors intended for use in the failed Belene nuclear power plant project to Ukraine. “Belene NPP is one of the most advanced nuclear power plant projects in Europe, and we..
The Council of Ministers approved a roadmap for the completion of Struma motorway. According to the schedule, an open tender for preliminary design is to be launched in February 2025 for the uncompleted Simitli-Kresna section. The route will be..
Maria Bakalova is set to star in Sylvester Stallone’s new film “My Masterpiece”, the professional film website IMDB writes. According to the official..
Experts from the Royal Netherlands Police are in Sofia for a series of trainings for their Bulgarian colleagues from the Border Police in the field of..
A photograph in the media of Minister of Labour and Social Policy Borislav Gutsanov (Bulgarian Socialist Party), MEP Kristian Vigenin (Bulgarian..
+359 2 9336 661