The planned annual repairs of Unit VI of Kozloduy NPP have been completed five days ahead of schedule. On November 1, at 1.41 am, it joined the country's energy system after an inspection and approval by the Nuclear Regulatory Agency.
The unit was stopped on September 29. For 31 days, the capacity of 1,000 megawatts was not part of the electricity market, which caused further rise of energy prices in Bulgaria.
Equipment maintenance has been performed and the unit has been refueled with fresh nuclear fuel. All the planned activities related to increasing the safety and ensuring the long-term operation of the unit have been carried out. The 5th nuclear power unit of Kozloduy is also operating at full capacity, the power plant's head Nasko Mihov said.
Most foreign workers in Bulgaria are employed in tourism, construction and transport. This information comes from Atanas Katsarchev, chief economist of the "Podkrepa" trade union, who spoke to BNR. He added that, due to the lack of medical personnel,..
Led by Prime Minister Rosen Zhelyazkov, the Bulgarian delegation is visiting Rome and the Vatican on 22 and 23 May 2025. Traditionally held on the eve of 24 May, the Day of the Holy Brothers Cyril and Methodius, the Bulgarian alphabet, enlightenment,..
Bulgaria is represented with its own stand at the 4th China-CEEC Expo & International Consumer Goods Fair, which is being held from May 22 to 25. "The interest of Chinese consumers in Bulgarian products is undeniable. Yogurt,..
Strengthening bilateral economic cooperation between Bulgaria and Italy, participation in joint defense projects and achieving peace in Ukraine were the..
The retirement age should not be changed – this is the position expressed by Social Minister Borislav Gutsanov talking to the Bulgarian National..
Bulgarian virtual influencer Ahinora made her debut in the European Parliament, greeting MEPs. Ahinora is the first Bulgarian avatar, and now an..
+359 2 9336 661