“92% of the Gas Interconnector Greece-Bulgaria, ICGB, is ready. The interconnector will be ready by the end of June, and will be tested with gas as of July,” Teodora Georgieva, Bulgarian Executive Officer of the company ICGB which is constructing the interconnector said for public service TV BNT.
"The 182-km. long linear part of the pipeline is ready. The pipes have been laid and covered, tests have been conducted. Besides Covid-19, the construction work has also been slowed down by delayed crane deliveries, but they too have now been tested. What remains is the construction of the gas stations in Stara Zagora in Bulgaria and in Komotini in Greece. The construction company is due to pay damages of EUR 90,000 per every day of delay after the beginning of 2022. The pipe’s capacity, which is 3 million cubic metres, and it has already been reserved," Teodora Georgieva said.
Bulgaria is making the necessary progress towards adopting the euro, according to representatives of the European institutions whom Finance Minister Temenuzhka Petkova met with. This progress will allow Bulgaria to request extraordinary convergence..
Financial and tax stability has been shaken in recent years so it is good that a government has been formed, said Vasil Velev, chairman of the Bulgarian Association of Industrial Capital, at a joint press conference of employers. "Romania was..
The Ukrainian parliament has authorized the purchase of two Russian nuclear reactors from Bulgaria, Euractiv reports. The energy committee of the Ukrainian parliament greenlighted the purchase of two old Russian nuclear reactors to expand the..
The budget for 2025 is feasible and will likely be the last one in Bulgarian leva, Minister of Finance Temenuzhka Petkova said in an interview with bTV...
+359 2 9336 661