550 megawatts of new gas capacities are going to be built at Varna thermoelectric power station on an investment of 450 million euro, the management of the station, with major shareholder the Movement for Rights and Freedoms’ honorary chairman Ahmed Dogan, has announced.
The two 275 megawatt blocs will be engineered from Siemens technology and will be built by Russian companies. Up to one-third of the gas used will be hydrogen produced by water splitting. The installation will be powered by an 80 megawatt photovoltaic park. The park will cover the area of the former coal ash dump. The technology was chosen because of its high effectivity, the Varna thermoelectric power plant management says. Under the contract signed the new station is to start functioning at the beginning of 2025.
Bulgaria has sufficient quantities of fuel and the 90-day reserves are secured at around 98%, Asen Asenov, Chairman of the State Reserve and Wartime Stocks State Agency, told bTV. The country has a gasoline reserve for 35 days and a diesel reserve..
Bulgaria’s President Rumen Radev has issued a decree appointing Deputy Minister of Foreign Affairs Maria Angelieva as Bulgaria’s Ambassador to Hungary. The decree was promulgated in State Gazette on Tuesday, reported BTA. Maria Angelieva graduated..
The new modular multi-purpose vessel of the Bulgarian Navy, ''Hrabri'' (Brave), was launched into Varna Lake from the pier of the MTG – Dolphin shipyard. Construction of the modular multi-purpose vessel began in 2022. It is the first of two..
The Sofia City Court has postponed the extradition case of Igor Grechushkin, the owner of a cargo ship linked to the explosion at the port of Beirut in..
The Road Infrastructure Agency (RIA) has proposed the introduction of temporary restrictions on the movement of heavy trucks weighing over 12 tons along..
Bulgaria has sufficient quantities of fuel and the 90-day reserves are secured at around 98%, Asen Asenov, Chairman of the State Reserve and Wartime..
+359 2 9336 661